| 05/16/01 |
General Dynamics Base Award |
| 06/14/01 |
Change ACT language |
| 10/16/01 |
Exercise line 0014 and update DD-254 form |
| 11/15/01 |
Add revised DD Form 254 |
| 02/07/02 |
Delete duplicate training courses under CLIN 0019 |
| 05/31/02 |
Add clarification to SSA deliverable in TRN & to the C&A section of the SOO |
| 05/31/02 |
Add requirement that the contractor comply with EU Policy |
| 07/05/02 |
Add worker's compensation insurance & anti-terrorism protection |
| 08/06/02 |
Add lab acceptance provisions to Section E |
| 08/16/02 |
Reconfigure network element management software |
| 09/19/02 |
Change FAD for NS40-09 |
| 11/13/02 |
Add Telephonica provision |
| 11/05/02 |
Add item 0023/CLIN 0700, change section H |
| 12/09/02 |
Stop base IT modernization work in Sigonella, Italy until 1/30/03 |
| 03/18/03 |
Date changes to Sigonella stop work /terminate issues in NS40-13 |
| 04/10/03 |
Add revised DD 254 Form |
| 04/11/03 |
Update designation of the ACOR |
| 09/02/03 |
Correct/delete building list for sites |
| 09/05/03 |
Adjust the order price for costs associated with design changes |
| 09/15/03 |
Add CLINS 0037 & 0038, delete ACOR |
| 09/23/03 |
Correct building lists, equitable adjustment for Sigonella start-up, update CLIN |
| 09/24/03 |
Definitize NS40-19, incorporate option line items |
| 11/18/03 |
Admin changes to previous mods |
| 11/24/03 |
Item 0043, 0044AX, 0044BR, 0046AX, 0046BR, 0046BU exercises |
| 01/08/04 |
Update designation of COR and ACOR |
| 01/28/04 |
SubCLINs under items 0044, 0045, 0046 exercised |
| 02/25/04 |
Item 0044AG, 0044BA, 0044BD, 0044BG, 0044BK, 0046AG, 0046BA, 0047DB, 0046BG exercised |
| 04/01/04 |
Incorporate changes to TRN, change section H |
| 05/13/04 |
Cancel item 0045AD and de-obligate funds |
| 06/28/04 |
PoP changes to Far East Locations |
| 08/19/04 |
PoP changes to Far East Locations and Sigonella |
| 10/15/04 |
Changes to section H |
| 10/14/04 |
PoP changes to Diego Garcia and Sigonella |
| 01/18/05 |
PoP changes to Diego Garcia and Sigonella |
| 01/17/05 |
COR change |
| 02/26/04 |
General Dynamics base award |
| 03/08/04 |
Admin Mod |
| 03/09/04 |
Admin Mod |
| 04/02/04 |
Add new line items 0007-0010 |
| 04/28/04 |
Add new line items 0011-0025 |
| 07/15/04 |
Add new line items 0026-0049 |
| 07/15/04 |
Add new line items 0050-0054 |
| 07/19/04 |
Admin change |
| 07/27/04 |
Line item 0055 requirements change |
| 07/27/04 |
Admin change to line item 0055 |
| 08/13/04 |
Definitize value of line items 0007-0010 |
| 10/13/04 |
Definitize value of line items 0011-0025 |
| 10/19/03 |
Definitize value of line items 0026-0049 |
| 01/04/05 |
Section H change |
| 01/28/05 |
COR change |
| 06/23/05 |
Change PoP end date to 07/15/05 |
| 07/18/05 |
Change PoP end date to 08/17/05 |
| 08/11/05 |
Change PoP end date to 08/31/05 |
| 08/25/05 |
Add new line item 0056 |
| 10/25/05 |
Exercise Option Year 2 |
| 11/25/06 |
Incorporate TDLs to OY3, incremental funding for OY3, change COR |
| 12/14/06 |
Incremental Funding for Option Year 3 |
| 02/13/07 |
Realign unused ceiling amounts from base year to OY3 and OY4 |
| 04/11/07 |
Incremental funding for OY3 |
| 09/28/06 |
Purchase Dell GX620 NIPR/Dell GX629 SIPR |
| 09/28/06 |
Purchase Dell GX620 NIPR/Dell GX610 SIPR |
| 03/08/07 |
Changes to CLIN 0001, 0002 and 0003 totals |
| 03/26/07 |
Add Naples and Souda Bay shipping location, realign quantities in CLIN 0001 |
| 04/12/07 |
Realign funding and update section B |
| 05/10/07 |
De-Obligate excess funds, update section B |
| 09/25/06 |
Purchase NIPR desktop |
| 03/19/07 |
Purchase of hardware for Bahrain and Guam |
| 03/26/07 |
Purchase of hardware for Bahrain |
| 05/08/07 |
Purchase of hardware for Bahrain |
| 05/08/07 |
Purchase of classified desktop for Napoli, Italy |
| 05/08/07 |
Purchase of hardware for Napoli, Italy |
| 09/28/06 |
Purchase additional equipment |
| 09/22/06 |
Purchase of Dell GX620 NIPR and SIPR |
| 08/07/02 |
Microsoft Premier Support Services Base Order |
| 12/14/06 |
Microsoft Premier Support Services |
| 09/18/06 |
Base Award for Replacement of ONE-NET Network Devices |
| 11/16/06 |
Change CLIN structure in section B, change FAD sheet info |
| 01/04/07 |
Increase CLIN 0001, exercise Option CLIN 2001 |
| 02/14/07 |
Exercise CLIN 0003, 1101, 2001, 3001, 4001, 5001, 6001, 7001, 9001 |
| 05/24/07 |
Increase CLIN 001, 0003, 1001 |